Preparation of land use plan (layouts)

Preparation of Land Use Plan

  1. Apply to the District Chief Executive with a base map from Survey Department.
  2. Application is forwarded to Physical Planning Department for designing within five (5) working days of submission.
  3. The initial design is subjected to public consultation for further inputs, recommendation and/or corrections within fourteen (14) months of submission.
  4. Technical committee meets to evaluate the application and makes recommendation to the Statutory Planning Committee (SPC) within fifteen (15) working days after public consultation.
  5. Statutory Planning Committee meets to approve/deny the application within ten (10) working days after the Technical Committee meeting.
  6. Pay the appropriate fee and collect your approved land Use Plan from the Physical Planning Department sixteen (16) months after submission of application.
  7. The Physical Planning Department then distribute the approved Land Use Plan to other sector agencies.